CONTROL AND ELIMINATION OF LEAKS ON LIVE AND UNDER PRESSURE, PREVENTIVE MAINTENANCE AND CORRECTIVE TO VALVES IN OPERATION
RELATION OF THE LOST OF ENERGY ACORDING TO THE SIZE OF THE HOLE AND THE FINANCIAL COST.

Being the cost of the steam $ 83.00/Ton of steam and consumes 70Kg of gas/Ton of steam, operating 8000 hours per year. In a pipe line it was found  a leak that had 5mm of diameter in which flues steam at 10 Atm (10.00 kgf/cm2).
It is observed a lost of 87 Kg/Hr. = 0.087 Ton/Hr. x 8000 Hrs/year
= 696.00 Ton-steam /year
= 696.00 Ton-steam/year x 0.070 Ton-gas/Ton steam
= 48.72 Ton-gas/year.
= 696.00 Ton-steam/year x $ 83.00 /Ton-steam
= $ 57,768.00 per year

   
SETEIN INTLS. S.A. DE C.V. is integrated by high qualified personnel , responsible of your safety and the quality in the service.
     
VALVE MAINTENANCE.
     
 
     
   
     
SERVICIOS TECNICOS INDUSTRIALES INTERNACIONALES S.A. DE C.V.
Bernardo Simonin No. 1411.
Colonia Guadalupe Victoria.
Coatzacoalcos,Veracruz
C.P. 96520, Mexico.
http://www.seteinintls.com
PHONES AND FAX
+52 (921) 21-3-86-79
+52 (921) 21-3-86-41
+52 (921) 21-3-86-15
E-mail: setein1@prodigy.net.mx
 
©2010 SERVICIOS TECNICOS INDUSTRIALES INTERNACIONALES, S.A. de C.V. All Rights Reserved..